Likewise, people ask, what is Schedule percent complete in p6?
The Schedule % Complete in Primavera P6 specifies how much of the activity's baseline duration has been completed so far. Computed based on where the current data date falls between the activity's baseline start and finish dates.
Also, how does p6 calculate remaining duration? Adding a date in the Expected Finish date field locks down the end date of the activity and forces P6 to calculate the Remaining Duration. In the above image you can see that an Expected Finish date of 27-Jan-15 has pulled the end date back to its original date and caused P6 to calculate a 6 day remaining duration.
Similarly one may ask, what is the percent complete rule?
0/100 Rule – this rule illustrates that once 100 percent of the task is completed, only then will the value be earned. Examples of this are testing or experimental tasks since you cannot get results until the task is completed.
What is a p6 schedule?
A Primavera P6 schedule is often required at the start of a project, regardless of whether it is simple or complex, to forecast the duration of the project and its activities. This is all done with the goal of delivering the projects deliverables to the quality standards while finishing on time and on budget.